Transportation

Cherokee Street Road Improvement

Scope:  Project includes widening the road to three (3) lanes, intersection improvements, and adding curb, gutter and sidewalks.  The project will also include right-of-way purchase.

Project Budget:           $1,459,134     (2005)
                                       $5,325,410     (2011)

Project Schedule:  Right-of-way acquisition underway

Stanley Road and Collins Road Improvement 

Scope:  Phase I: Widen Stanley and Collins Roads; add sidewalk along Collins Road and roundabout at the intersection of Stanley and Collins Road.   Phase II: Widen and realign Stanley from Collins to RR Crossing (City/County Line).

Project Schedule:  Completed

Cobb International Boulevard 

Scope:  Upgrade road to industrial standards

Project Budget:  $1,500,000

Project Schedule:  Deferred due to lack of funding

Pine Mountain Road from Cobb Parkway to Ellis Road 

Scope:  Provide safety and operational improvements along the entire corridor of Pine Mountain Road (1.5 miles) as well as to improve the intersection of Shillings Road with Pine Mountain Road and make safety improvement to Ellis Road.  Pine Mountain Road will be widened to three 12-ft. lanes, sidewalks will be added to both sides of the road, and retaining walls will be constructed to minimize right-of-way impacts. Ellis Road will have some safety improvements where it ties to Pine Mountain Road. Right turn lanes will be added to the intersections with Pine Mountain Way and Cobb Parkway. The project will end at Cobb Parkway.  Project will tie to Cobb Department of Transportation project that will extend the improvements to Stilesboro Road.

Project Schedule:  Completed

Depot Park Improvements (continued into 2016)

Scope: Depot Park Master Plan – amphitheater, plaza, parking improvements

Project Budget:  $2,100,000

Project Schedule:  Phase 1-5 completed. Phase 6 & 7 bidding Spring 2020Phase 1-5 completed. Construction underway for Phase 6 & 7. Estimated completion Fall 2020.

Smith-Gilbert Gardens (continued into 2016)

Scope: Construct a multi-purpose facility to host events

Project Budget:  $1,800,000

Project Schedule:  Phase 1 bidding Spring 2020Phase 1 estimated to begin Spring 2020. Phase 1 includes additional parking & site improvements.

Infrastructure Improvements 

Scope: Repairs will be done throughout the City during course of the SPLOST program.

Project Budget:  $1,167,152

Project Schedule:  Ongoing Work; sidewalk projects, curb, gutter, stormwater

Resurfacing 

Scope:  Resurfaced various roads throughout the city

Project Budget:     $439,890

Project Schedule: Ongoing

Parks & Recreation

Skate Park Project 

Scope: Regional concrete outdoor skating facility to include street skating and transition skating areas and multiple bowls.

Project Schedule: Completed

KSP Open 506  March Rad 7 March Rad 5

Community Center Renovation 

Scope: Renovate/refurbish existing classrooms, meeting rooms, dance rooms and added pottery class addition.

Project Schedule: Completed

CeramicStudio_ClassCeramicStudio_Exterior

Swift Cantrell Park Improvements 

Scope: Improvements including additional parking, landscaping, restroom and irrigation.

Project Schedule: Completed

NewSwiftCantrellParkingLotNewSwiftRestroomBldg

Click here for a spreadsheet of 2011 SPLOST projects